On 29th October 2024, there will be a scheduled power shutdown in Needamangalam and nearby areas for monthly maintenance at the Needamangalam 110/33-11 KV SS substation. The outage will last from 9:00 AM to 2:00 PM.
Thiruvarur Power Shutdown Schedule for 29th October 2024
Content | Details |
---|---|
Date of Outage | 29-10-2024 |
Time | 09:00 AM – 02:00 PM |
Substation | Needamangalam 110/33-11 KV SS |
Affected Locations | Sarvamanyam, Needamangalam, Pachakulam, R.P.Chavadi |
Total Areas Affected | 4 |
Maintenance Type | Monthly Maintenance |
The following locations will be affected:
- Sarvamanyam
- Needamangalam
- Pachakulam
- R.P.Chavadi
Residents should plan ahead by completing tasks requiring electricity before the outage and disconnecting sensitive appliances to prevent any damage during the restoration of power.
How to Check the TNEB Thiruvarur October 29, 2024 Shutdown Status
- Visit https://www.tnebltd.gov.in/.
- Select Circle for Thiruvarur.
- Enter the CAPTCHA code displayed.
- Click Submit to view the latest updates on the shutdown.