Scheduled power outages will occur in Krishnagiri district on 26th September 2024 due to maintenance at multiple substations. The power will be cut between 9:00 AM and 5:00 PM for the following areas:
Content | Details |
---|---|
Date of Outage | 26-09-2024 |
Time | 09:00 AM – 05:00 PM |
Substations | Uthangarai 110/33 KV SS, Krishnagiri 110/33-11 KV, Kammandoddy 110/11 KV, SIPCOT – II PHASE 110/22 |
Affected Locations | Uthangarai, Kondampatty, Krishnagiri Town, Kammandoddy, Sipcot Phase -2 |
Total Areas Affected | 4 |
Maintenance Type | Monthly Maintenance Work |
- Uthangarai Substation: Uthangarai, Kondampatty, Chennappanaiyakanoor, Perumalkuppam, Mittapally
- Krishnagiri Substation: Krishnagiri Town, Rajaji Nagar, Collectorate, Oldpet, Housing Board phase 1 and 2
- Kammandoddy Substation: Kammandoddy, Koneripally, Pathakottai, Gangojikothur, Nallur
- SIPCOT – II Phase Substation: Sipcot Phase – 2, Bathalapally, Kumudhepally
Technicians will inspect transformers, conduct repairs, and perform equipment upgrades to improve the electrical supply network. It is advised that residents prepare for the outage by completing necessary tasks in advance and unplugging electrical devices.
How to Check the Krishnagiri Power Shutdown – 26th September 2024
- Visit the TNEB website: https://www.tnebltd.gov.in/.
- Choose the Circle corresponding to Krishnagiri.
- Enter the CAPTCHA code correctly.
- Click Submit to view the current updates on the power shutdown.
Regularly checking the website will keep residents updated on any changes to the schedule.